We are building a new extension, in the North East, with all new plumbing just started to get some estimates and the first one just came in not sure if it's high or not.

the plumbing is rough and finish for

kitchen sink, dishwasher, ice maker, pot filler

two piece powder room toilet and sink

four piece master bedroom

2 three piece bathroom

laundry room washing machine

three outdoor hose bibs

Total for this=$16,500

Gas rough and finish plumbing for gas line to stove and first floor dryer, boiler, fireplace

Total=$3,200

Boiler supply and install 1 Navien boiler NPE210a-180000 BTU boiler only

supply and install all necessary material for 3 zone on boiler

supply and install 1 50 gallon storage tank

two zones can either be used for radiant or two fan coil unit

Total=$10,500

Radient heat for 1,700 sq feet

Total=$13,000

TOTAL JOB $43,200