Proposed Payment Schedule

gorilla_x
16 years ago

I'll be pitching this to the PB this week. From I gathered here, a lot of PBs front load the contract, collecting 80% or more at the conclusion of gunite.

In Central FL, but will not have a screen. Fence, alarm, decking/coping are separate contracts between between me and other companies.

Rough cost breakdown of pool:

- 7' deep 832 SF + 48 SF spa: ~$30K

- Equipment: ~$10K (for Aquacal H155 heat pump, IntelliFlow 4x160, Easy Touch 8 Pool/Spa, CNC Plus 420 SF filter, 3 IntelliBrite LEDs)

Equipment is 26% of the bill. I do not know what plumbing costs, so I'll guess. Based on what I've read on the forum, I'll pitch the following:

- Layout/Dig/Steel Complete (Draw #1): 20%

- Gunite Complete (Draw #2) : 30%

- Plumbing Complete (Draw #3): 10%

- Tile and Pool Equipment Installed (Draw #4): 30%

- Final Payment: 10% due at Pool School

Seem reasonable?

-Gorilla