Philadelphia Kitchen - Week 3

Carrie B
8 years ago

Today's goals: prep subfloor for cork floating floor scheduled to arrive Wednesday, finish insulation & add drywall.

I forgot to mention last week that they uncovered another hearth - this one in the kitchen. I now know of five - 2 on the first floor, 2 on the second. The third floor has one, and I'm thinking there may very well be another under what is now the jacuzzi tub.

One glitch uncovered so far today - the OTR microwave was supposed to vent directly out the back. Contractor realized that the heating duct is directly behind the center of the microwave. Two options were to either go with recirculating, or redirect the vent up & out behind the open shelved cabinet above it, thus losing a portion of the cabinet space. I opted for the second.