We got back this bid and it seems pretty thorough. The only things that I can see that need added are that the windows are to be installed per manufactuers instructions and that it's to be framed at 16" OC. He does all his framing at 16" OC, but I'd prefer to have it in writing. :o)


"We hereby submit specifications and esimates for:

Fastening a 2"X8" PT sill plate to top of blockwork. Install, block and straighten dropped sills and TJI truss floor. Deck with 3/4" Advantec. All sub-flooring to be glued and fastened with 1 3/4" screws. Frame, brace, and straighten 1st floor walls. Install 2"X4" blocking mid-span of all studs. Dining room, foyer, and bedroom #2 have 11" ceilings. Frame & deck second floor system. Frame stairs to 2nd floor. Frame 2nd floor walls as required for future living area. Install all porch beams, garage beams, all remaining ceiling joists, knee walls, and roof system. Deck roof with 1/2" OSB and cover with 30 lb felt. Frame all cornice work and overhang for trim. Install 1/2" OSB on all outside walls and cover with housewrap. Install exterior doors & windows and cover with window wrap. Front porch beams to have a radius shape. Frame 2 dormers on front elevation. Frame for garden tub in masterbath. Frame deck and steps in rear. Does not include installation of permanent porch columns. A thorough clean-up is to be done upon completion. Approximate completion 5 1/2 weeks. Weekly draws based upon percentage of work completed."

We will have a seperate crew coming to do the exterior trim work, columns, and shake siding. Do you see anything else that we should add?

Comments (20)