Timing - Finish Rough Grade, Gravel, Driveway, Patio, Finish Grade

whaas_5a
3 years ago

It seems each trade has a preference.

Has anyone come across the best approach for the order of activities?


For concrete contractor installing drive and patio

1) Install patio gravel base

2) Finish Rough Grade (spread onsite topsoil to master grading plan)

3) Fine tune patio and driveway gravel base

4) Install concrete drive

5) Install concrete patio

6) Final finish grade

7) Install lawn


For separate patio and drive concrete contractor

1) Install patio gravel base

2) Install concrete patio

3) Finish Rough Grade (spread onsite topsoil to master grading plan)

4) Fine tune driveway gravel base

5) Install concrete drive

6) Final finish grade

7) Install lawn

Comments (2)