SHOP PRODUCTS
Houzz Logo Print
going_northwest

Kitchen has been demo for 2 months, contractor has only worked 3 days

Going Northwest
5 years ago

I’m wondering what to do with the contractor we hired for a kitchen remodel. We signed a contract back in December with a start date in early February. The scope of his work included demo, moving a cold air return, installing cabinets, plumbing the new sink, moving a water supply line to the fridge, installing a duct to vent our new hood outside, new countertops (which is subbed out and we’ve fully paid for), installing a backsplash, and installing new appliances (with associated electrical work).

Unfortunately the jobs our contractor lined up before ours took longer than expected and within a week of his initial start date we were told he was at least two weeks behind at that point. They did come and did the bear minimum demo needed to get out of the way for our flooring contractor. For reference, once learning of his delay we took it upon ourselves to do 80-90% of the demo and disposal to help him get things back on track. The initial delay wasn’t a terribly big deal as our flooring contractor took a little more time that expected. However, again at the last minute we were told the other jobs were still behind and our job would be further delayed to a month. Our contractor made an effort to begin work on our project, but over the course of a few weeks made very little progress - basically just the return vent and finished demoing our old backsplash. He was trying to start our job while still being behind on his previous jobs. They also have a large, lucrative contract lined up after ours that’s going to be significantly delayed too. To pile on top of that, our contractor let us know the middle of last week that he has pneumonia and now we have no clue when he will move over to our job. It’s now been over 2 months since our contractor was supposed to start and we’ve been without a kitchen that entire time. In addition, our flooring contractor is waiting for the kitchen to be done before doing the final buffing and sealing of the wood floors, so we basically have very limited use of the main floor of our house.

We’ve complied with all the conditions in the contract including the payment schedule that included a ½ labor deposit on their first day in earnest working on our project, which we feel a little swindled on this because we’ve maybe had 3 full days of work since the very beginning and only 1.5 of those days after paying this deposit. At this point we’ve paid for all material, the countertops (including install by the sub), and the ½ labor deposit. We feel getting the countertop contract moved directly to us would be pretty easy.

When our contractor called us last week to let us know he has pneumonia he told us that we could terminate the contract with him. We let our contractor know that we would like to keep the contract with him and have him complete the work. We really would like to have our kitchen back in working order with a newborn at home.

We want to trust that our contractor is doing his best and has just had a spell of bad luck, but need to be prepared if that’s not the case. Our pessimistic thought is that with his large contract waiting in the wings is that our contractor simply wants to find a way to skip our job. What should we be doing now to protect ourselves in the event we need to terminate the contract and seek another contractor? If we need to go this route, we won’t have the project done for another 3-4 months due to the fact everyone we talk to has full schedules and will be without a kitchen the entire time.

Any advice or suggestion on how to move forward would be greatly appreciated.

The kitchenless family

Comments (15)