Tomorrow is the big day. Layout and digging! I have found other owner builder threads so useful, I figured I would share my experience.

Here is what has happened so far. I found a pool designer and had my plan drafted and engineered. Pulled permits from the city. Spent a fair amount of time collecting bids. Original budget looks something like this:

Estimate

Design/Engineering 925

Permits 950

Excavation 2,500

Steel 2,000

Plumbing 6,000

Pool Equipment 7,000

Electric 4,500

Gunite 7,500

Tile 3,500

Decking 7,000

Plaster 7,000

Pool Slide 2,500

Safety 3,500

Start-up 1,000

Solar 5,000


TOTAL 59,000

I rounded up on everything - so the actual costs may come in lower.

Pool specs

18' x 32' free form

24" raised bond beam in corner with sheer decent

SR Smith Turbotwister pool slide

7' spa with 13 jets

In-floor cleaning system

Pentair Equipment including Intelliflo pump and

Intellitouch automation

SWG

Solar

(2) wetdeck bubblers

depth 3'6" to 7'6"

Here is the plan:

{{gwi:2038551}}

Here is the bare land - waiting for water!

{{gwi:2038810}}

Tentative schedule

Excavation - June 15th & June 16th

Plumbing - June 18th - June 20th

Rebar - June 21st & June 22nd

Electric - June 25th - June 27th

Pre-Gunite Inspection - June 28th!!

Can't think past gunite right now. Will post more after the dig! Wish us luck.