Reality check- does this timeline make sense?

thrilledtoremodel
14 years ago

Hi guys-

Only a few weeks left! here's how I think it will work out= please tell me if it makes sense.

-July 5th (sunday): Neighbor friend/plumber will come over in the evening to disconnect sink/DW connections. Will also need water supply for new fridge location.

-July 6th: Cabinet removal 9-11:30 am (being done by friend/junk removal guy). Demo work (soffits destroyed, fridge recessed into bathroom closet) 12 pm- 5 pm?

-July 7th & 8th: Electrician day. Adding recessed lights, 2 pendants, extra electricity for electric range etc. 8 am- 5 pm?

-July 9th/10th/11th: (Saturdays ok they said)Flooring guys rip up flooring & put down raw oak. Will eventually do 3 coats poly. Flooring guy mentioned roughly 10 days from start to when cabinets can be installed- so I take this to mean July 9th plus 10 days= ~July 19th/20th.

-July 20th (Monday): Cabinet installation!

-July 21st: Granite guy templates. Also cabinet guy can do finishing stuff that day too.

-July 24th (Friday): Granite install (morning). Electrician finishing (afternoon)- pendants put up, electric range & GE advantium install, etc.

-July 27th/28th (Mon/Tues): Painter comes, does plastering to repair where soffits were...and then paints ceiling, trim, walls.

Wed July 29th- eating in our new kitchen???

(PS I'm starting a new job August 3rd- so I have a deadline to get this all done!) :)