SHOP PRODUCTS
Houzz Logo Print
webuser_89367023

Added cost for new home build elevation

HU-89367023
3 years ago

We contracted to build a winter home in Florida on 5/31/19. We purchased the lot in an established subdivision, but the purchase was contingent on the builder checking it out and verifying it was buildable, not in a flood zone, etc., which they did. The builder gave us a 10-12 mo. estimate for completion, which they have far exceeded.


In July 2019 we signed a site plan for the house, to be centered on the lot, but later found a new site plan was drawn up, without our signature, moving the house 2 ft. to the left to allow for the septic field. After numerous delays upfront (permitting, truss plan changes, etc.), the footer was finally poured in Feb. 2020, at which time we went down to see the progress & meet with the builder. We were told then that they were just made aware of changes in health dept. regulations for the septic system which would require that we either install a septic pump, for a few thousand dollars, or raise the elevation of the home 3 - 4 ft., at a cost of $7,000. We later found out that they were made aware of these changes in July, but failed to tell us. Due to our fear of electrical outages during hurricane season, we opted for the change in elevation. The added cost was not itemized, only listed as "site work" for septic. It was verbally stated that the added cost was to cover the extra height of walls, as well as the fill needed to be brought in to raise the elevation.


Since that time, the ICF walls have gone up, the roof trusses and underlayment were put on, fill was brought in & compacted to raise the interior elevation, & the floating slab was poured. Electrical & plumbing work continued on the house, and the septic tank and lateral lines were put in, but no exterior fill has ever been brought in. When we asked, we were told they were encountering problems with how to achieve an appropriate slope without causing drainage problems for the one neighboring house, since our build ended up closer that property line than originally planned. We have pressed them repeatedly for how this was going to be resolved, and we've been told they might have to put in a retaining wall, they were going to call in an engineer, etc. They also discussed the possibility of having to have steps installed to entryways, which we opposed to given our ages. The builder himself at one point told us on the phone that they could put in curved ramps from the doorways to the drive to avoid having to put in steps. He also assured us that none of this exterior elevation work, whether it be a retaining wall or a slope, would cost us any additional money.


Now, about a month after that conversation, the project manager mentioned that she knew we wouldn't be happy, but the exterior work would require additional money, and that the $7,000 we paid was only for the walls and interior fill. We don't HAVE any additional money. We paid for the house out of our own savings, which is depleted. The $7000 was a cushion we were holding out to later install fencing and buy furnishings. Do we have any recourse on this? They have not stated how much extra they're talking about, and we are holding out hope that the builder will stand by his word, but we want to be prepared for how to handle this. Any advice?

Comments (13)