as part of remodeling, we are trying to remove two walls (marked "X" in the picture of lengths 36" and 84"). These walls are located in the first floor directly below our master bedroom and master bath. We have a finished basement on the floor below these walls.

We believe the side wall (113")is load bearing since we see a header beam running in the basement. I'm assuming the upper floor must use the same construction. There is a wall in the identical place in the second floor (wall of master bath).

To remove the 84" wall the idea is to create a header and put two supporting post in the either end of the walls (length 174"). We are fine without a flushed ceiling.

We are not DIYers and the contractor suggest to use Simpson Double Shear Joist Hangers for the side wall (36") opening. ANy thoughts on how complicated this is? Is it a reasonable approach?