17 years ago

OK when the builder and I looked over my lot we agreed he would do all site work. There needs to be a minimum of 30 feet of side entrance garage. The lot grades down away from garage on the side. It winds up at a line of trees that mark the property line. He had a plot plan report done by an engineer. It shows the need for a drain and cast in place concrete retaining wall. My builder agreed to it. now that the foundation has been poured he is saying neither is needed. I dont want my driveway eroding away. He sais the first engineer was wrong and we will be fine. the contract states that all normal site work is his responsibility. He saw the lot and had a surveyer look everything over before we sighned the contract. The contract even sais he will put the drain on property line!

Hesais the new engineer feels it is not needed. Should I request he have the new engineer put this in writing?