10 years ago

To Worthy and others in the know. Had a discussion last night about how long you should let your footers cure before basement walls are added? This is Midwest, 18"w x 12" h footers, then 9' basement walls added. we are still a few weeks out from excavation (to virgin soil and soils test). what I have been seeing around here is footers followed by basement walls after about 2-3 days of curing time? came up in discussion last night of at least 10 days.

Have not discussed timeline with my builder yet, wanted thoughts from here. Thanks