I poured the concrete foundation pads today. I am making it 12X12, by adding 4 feet to our existing porch. It should take me just a few hours to complete the floor. Then on another day, just a few hours to frame up the walls. (two feet on center) Then, a few hours for the roof. Then I will add my 4X8 PolyCor panels from FarmTek. I should complete all the framework next week, if the hurricane dodges us. I anticipate the project to be completed within two to three weeks, less the shelving. (provided that I can get the PolyCore panels within that time from FarmTek) I will order the panels next week. In this pic, where you see the window, I am going to put a door there so I can enter through the laundry room in the house. I will also have an exterior door on the north end of the greenhouse. Not much to this pic, but at least I have started!! :-)